Practice questions › Site Management › Site Management

Site Management Site Management practice questions

10 free questions with answers and explanations. Try each one, then tap “Show answer”.

  1. 5 · Design coordination

    1. A drawing revision changes the position of a service route after installation has started. What should the team do?

    • A. Confirm the current approved revision and assess the change before proceeding
    • B. Continue using the superseded drawing
    • C. Ask each trade to interpret a different revision
    • D. Remove revision identifiers
    Show answer

    Answer: A. Confirm the current approved revision and assess the change before proceeding

    Work should be coordinated against controlled, current information with changes assessed and communicated.

  2. 5 · Waste management

    2. Why segregate construction waste where practicable?

    • A. To support safe handling, reuse and appropriate recycling or disposal
    • B. To mix incompatible materials
    • C. To remove waste records
    • D. To increase skips overflowing
    Show answer

    Answer: A. To support safe handling, reuse and appropriate recycling or disposal

    Segregation can improve recycling and ensure different waste streams are handled correctly.

  3. 4 · Programme management

    3. What is the purpose of a construction programme?

    • A. Coordinate activities, sequence, resources and milestones over time
    • B. Replace the drawings
    • C. Guarantee no delays
    • D. Record only completed payments
    Show answer

    Answer: A. Coordinate activities, sequence, resources and milestones over time

    A programme helps plan and coordinate work, dependencies, resources and progress against milestones.

  4. 5 · Programme coordination

    4. A subcontractor is delayed and its work affects the next trade. What should the site manager do first?

    • A. Review the programme and coordinate a revised sequence with affected parties
    • B. Allow every trade to work in the same area simultaneously
    • C. Change the completion date without informing anyone
    • D. Ignore the delay until handover
    Show answer

    Answer: A. Review the programme and coordinate a revised sequence with affected parties

    Programme coordination requires understanding dependencies and communicating revised sequencing.

  5. Safety

    5. Which regulations cover hazardous substances such as cement dust and solvents?

    • A. RIDDOR
    • B. COSHH
    • C. LOLER
    • D. CDM only
    Show answer

    Answer: B. COSHH

    Control of Substances Hazardous to Health.

  6. 5 · Emergency planning

    6. What should workers know about the site's emergency arrangements?

    • A. How to raise the alarm, evacuate, reach the assembly point and report missing persons
    • B. Only the location of the canteen
    • C. How to restart every machine
    • D. The names of all suppliers
    Show answer

    Answer: A. How to raise the alarm, evacuate, reach the assembly point and report missing persons

    Workers need clear, site-specific instructions for alarm raising, evacuation and accountability.

  7. 2 · Working at height

    7. A ladder is damaged and unstable. What should happen?

    • A. Do not use it; report it and arrange suitable equipment
    • B. Ask someone to hold it
    • C. Use it for heavy loads
    • D. Hide damage with tape
    Show answer

    Answer: A. Do not use it; report it and arrange suitable equipment

    Damaged access equipment should be removed from use and reported.

  8. Safety

    8. Under LOLER, equipment used to lift people must have a thorough examination at least every

    • A. 6 months
    • B. 5 years
    • C. week
    • D. 12 months
    Show answer

    Answer: A. 6 months

    Other lifting equipment: at least every 12 months, unless a written scheme says otherwise.

  9. Quantities

    9. How much concrete is needed for a slab 3 m long, 7 m wide and 250 mm thick?

    • A. 21 m³
    • B. 5.25 m³
    • C. 10.5 m³
    • D. 52.5 m³
    Show answer

    Answer: B. 5.25 m³

    Volume = 3 × 7 × 0.25 = 5.25 m³ (convert mm to m first).

  10. 4 · Near-miss reporting

    10. A worker narrowly avoids being struck by a falling object. No one is injured. Why report it?

    • A. It can reveal failures and help prevent a future injury
    • B. There is no value because no injury occurred
    • C. Only injuries need to be reported internally
    • D. It automatically proves misconduct
    Show answer

    Answer: A. It can reveal failures and help prevent a future injury

    Near misses provide evidence of hazards and control weaknesses before someone is harmed.

Want more Site Management Site Management questions?

Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.

Practise free in the web app Practise on Telegram

About the Site Management on Mock Night · Original practice questions; not affiliated with the exam board.