NDT Penetrant testing (PT) practice questions
10 free questions with answers and explanations. Try each one, then tap “Show answer”.
- Interpretation
1. Under ASME, a linear indication is one whose length is
- A. equal to its width
- B. less than its width
- C. more than three times its width
- D. more than 1 mm only
Show answer
Answer: C. more than three times its width
Otherwise it is a rounded indication.
- Cleaning
2. Vapour degreasing and solvent cleaning before PT are used to remove
- A. magnetism
- B. the base metal
- C. fluorescence
- D. oils and greases
Show answer
Answer: D. oils and greases
Contaminants stop penetrant entering defects.
- Process
3. Low part temperatures generally require
- A. no developer
- B. a longer penetrant dwell time
- C. a shorter dwell time
- D. fluorescent light only
Show answer
Answer: B. a longer penetrant dwell time
Penetrant becomes more viscous when cold.
- Materials
4. Fluorescent penetrant sensitivity levels run from ½ (lowest) to
- A. 100
- B. 2
- C. 10
- D. 4 (ultra-high)
Show answer
Answer: D. 4 (ultra-high)
Higher levels find finer cracks.
- Types
5. Which type of penetrant is generally more sensitive?
- A. Fluorescent
- B. Visible (red)
- C. Neither can find cracks
- D. Both are identical
Show answer
Answer: A. Fluorescent
Fluorescent indications glow under UV-A light.
- Principles
6. Penetrant testing relies mainly on
- A. sound reflection
- B. capillary action
- C. X-ray absorption
- D. magnetism
Show answer
Answer: B. capillary action
The penetrant is drawn into surface-breaking openings.
- Process
7. Under ASME Section V, the standard temperature range for PT is
- A. 20 °C to 30 °C only
- B. 0 °C to 100 °C
- C. -10 °C to 40 °C
- D. 10 °C to 52 °C
Show answer
Answer: D. 10 °C to 52 °C
Outside this range the procedure must be qualified.
- Materials
8. A lipophilic emulsifier is
- A. oil-based and applied after the penetrant dwell
- B. a cleaner used before penetrant
- C. a developer
- D. water-based remover
Show answer
Answer: A. oil-based and applied after the penetrant dwell
Hydrophilic removers are water-based.
- Materials
9. With post-emulsifiable penetrants, which time is most critical to control?
- A. Time to read the procedure
- B. Shelf life of the developer
- C. Emulsification time
- D. Drying time of the cleaner
Show answer
Answer: C. Emulsification time
Too long and penetrant is removed from defects.
- Process
10. If a part must be re-inspected, it should be
- A. wiped and inspected again
- B. magnetised
- C. fully cleaned and processed again from the start
- D. just given more developer
Show answer
Answer: C. fully cleaned and processed again from the start
Old penetrant in defects can give unreliable results.
Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.
Practise free in the web app Practise on TelegramMore NDT practice
About the NDT on Mock Night · Original practice questions; not affiliated with the exam board.