Project Management Agile & Product Owner practice questions
10 free questions with answers and explanations. Try each one, then tap “Show answer”.
- Product owner
1. The commitment for the Product Backlog in the 2020 Scrum Guide is the
- A. Velocity
- B. Definition of Done
- C. Product Goal
- D. Sprint Goal
Show answer
Answer: C. Product Goal
The Sprint Backlog's is the Sprint Goal; the Increment's is the Definition of Done.
- Flow
2. A Kanban team has 6 items in progress and finishes 4 items a day. Using Little's Law, what is the average cycle time?
- A. 0.67 days
- B. 1.5 days
- C. 10 days
- D. 24 days
Show answer
Answer: B. 1.5 days
Cycle time = WIP ÷ throughput = 6 ÷ 4 = 1.5 days.
- Flow
3. A Kanban team has 10 items in progress and finishes 2 items a day. Using Little's Law, what is the average cycle time?
- A. 5 days
- B. 20 days
- C. 12 days
- D. 0.2 days
Show answer
Answer: A. 5 days
Cycle time = WIP ÷ throughput = 10 ÷ 2 = 5 days.
- Forecasting
4. A team's last three velocities were 23, 27, 21 points. About how many Sprints will a 200-point backlog take (rounded up, using the average)?
- A. 20 Sprints
- B. 8 Sprints
- C. 10 Sprints
- D. 9 Sprints
Show answer
Answer: D. 9 Sprints
Average velocity ≈ 24; 200 ÷ 24 ≈ 8.3 → 9 Sprints.
- Forecasting
5. A team's last three velocities were 25, 30, 22 points. About how many Sprints will a 200-point backlog take (rounded up, using the average)?
- A. 10 Sprints
- B. 8 Sprints
- C. 20 Sprints
- D. 7 Sprints
Show answer
Answer: B. 8 Sprints
Average velocity ≈ 26; 200 ÷ 26 ≈ 7.7 → 8 Sprints.
- Scrum
6. A Scrum Team is typically
- A. exactly 12 people
- B. one person
- C. at least 20 people
- D. 10 or fewer people
Show answer
Answer: D. 10 or fewer people
Smaller teams communicate better.
- User stories
7. The INVEST criteria for good user stories include Independent, Negotiable, Valuable, Estimable, Small and
- A. Testable
- B. Tracked
- C. Timeboxed
- D. Technical
Show answer
Answer: A. Testable
Coined by Bill Wake.
- Scrum
8. Under the 2020 Scrum Guide, what are the three accountabilities in a Scrum Team?
- A. Team lead, architect and coder
- B. Project manager, tester and analyst
- C. Sponsor, user and supplier
- D. Developers, Product Owner and Scrum Master
Show answer
Answer: D. Developers, Product Owner and Scrum Master
There are no other titles in Scrum.
- Product owner
9. Who is accountable for ordering the Product Backlog?
- A. The Developers
- B. The stakeholders
- C. The Product Owner
- D. The Scrum Master
Show answer
Answer: C. The Product Owner
The PO may delegate work but remains accountable.
- Forecasting
10. A team's last three velocities were 29, 27, 25 points. About how many Sprints will a 200-point backlog take (rounded up, using the average)?
- A. 8 Sprints
- B. 7 Sprints
- C. 10 Sprints
- D. 20 Sprints
Show answer
Answer: A. 8 Sprints
Average velocity ≈ 27; 200 ÷ 27 ≈ 7.4 → 8 Sprints.
Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.
Practise free in the web app Practise on TelegramMore Project Management practice
About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.