Project Management PMP practice questions

10 free questions with answers and explanations. Try each one, then tap “Show answer”.

  1. Business environment

    1. A new regulation will affect the project. What should the project manager do first?

    • A. Cancel the project
    • B. Assess the impact on the project
    • C. Ask the team to decide
    • D. Ignore it until audited
    Show answer

    Answer: B. Assess the impact on the project

    Then update plans through change control.

  2. People

    2. During Sprint Planning, a stakeholder tells the Developers exactly how they must build a selected Product Backlog item. According to the Scrum Guide, who decides how the work is turned into an Increment?

    • A. The Product Owner
    • B. The Scrum Master
    • C. The Developers
    • D. The stakeholder who requested the item
    Show answer

    Answer: C. The Developers

    Scrum Developers are self-managing and decide how to turn Product Backlog items into a valuable Increment. The Product Owner decides what is valuable and its order, not how it is built.

  3. Process

    3. An activity has an optimistic estimate of 4 days, a most likely estimate of 7 days and a pessimistic estimate of 16 days. Using the PERT (beta distribution) formula, what is the expected duration?

    • A. 7 days
    • B. 8 days
    • C. 9 days
    • D. 10 days
    Show answer

    Answer: B. 8 days

    PERT expected duration = (O + 4M + P) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8 days. The 9-day answer comes from the simple triangular average (4 + 7 + 16) / 3 = 9.

  4. People

    4. During Sprint Planning, the Developers help the Product Owner draft and clarify several new Product Backlog items. Later, a stakeholder asks who is accountable for the content and ordering of the Product Backlog. According to the Scrum Guide, who is it?

    • A. The Scrum Master
    • B. The Product Owner
    • C. The Developers who drafted the items
    • D. The stakeholder who requested the items
    Show answer

    Answer: B. The Product Owner

    The Product Owner is accountable for effective Product Backlog management, including ordering items. Others may help with the work, but the accountability stays with the Product Owner.

  5. Process

    5. During risk planning, the team identifies an opportunity: a supplier may deliver a component early if the team prepares the test environment sooner. The team takes steps to increase the probability of this outcome. Which response strategy is this?

    • A. Mitigate
    • B. Avoid
    • C. Transfer
    • D. Enhance
    Show answer

    Answer: D. Enhance

    Enhance increases the probability or impact of a positive risk. Mitigate, avoid and transfer are strategies for threats.

  6. Business environment

    6. In PRINCE2 7, which role owns the business case and is ultimately accountable for the success of the project?

    • A. The Project Manager, who prepares and updates it
    • B. The Executive on the Project Board
    • C. The Senior Supplier, who provides the resources
    • D. The Senior User, who specifies the needs
    Show answer

    Answer: B. The Executive on the Project Board

    The Executive chairs the Project Board, owns the business case and is ultimately accountable for the project. The Project Manager may draft and maintain documents, but accountability stays with the Executive.

  7. People

    7. A project manager believes that team members are naturally self-motivated, seek responsibility and can direct themselves toward shared goals. The manager therefore gives the team wide autonomy and minimal supervision. Which theory does this reflect?

    • A. McGregor's Theory X
    • B. McGregor's Theory Y
    • C. Herzberg's hygiene theory
    • D. Vroom's expectancy theory
    Show answer

    Answer: B. McGregor's Theory Y

    McGregor's Theory Y assumes people are self-motivated and responsible, which supports autonomy and trust. Theory X assumes people dislike work and need close control.

  8. Business environment

    8. A project delivers a self-service customer portal. Customers now resolve most queries online, and as a result the call-centre running cost falls by a measurable amount. In PRINCE2 terms, how is the reduced call-centre cost best classified?

    • A. An output
    • B. A product description
    • C. A benefit
    • D. A constraint
    Show answer

    Answer: C. A benefit

    A benefit is a measurable improvement perceived as positive by stakeholders, such as reduced cost. The portal itself is the output, and the change in customer behaviour is the outcome.

  9. People

    9. A newly assembled project team is polite and cautious. Members are unclear about their roles and depend heavily on the project manager for direction. Which stage of Tuckman's team development model is the team in?

    • A. Storming
    • B. Forming
    • C. Norming
    • D. Adjourning
    Show answer

    Answer: B. Forming

    Forming is the first stage: members are courteous, uncertain about roles and reliant on the leader. Storming would involve open conflict and challenge over roles and approach.

  10. Business environment

    10. A sponsor ranks three independent projects by benefit-cost ratio (BCR). The present value of benefits and costs is: Project X 700,000 / 400,000; Project Y 450,000 / 250,000; Project Z 300,000 / 240,000. Which project has the highest BCR?

    • A. Project X, because it has the largest net benefit
    • B. Project Y, with a BCR of 1.8
    • C. Project Z, because it has the lowest cost outlay
    • D. Projects X and Y, which have equal BCRs
    Show answer

    Answer: B. Project Y, with a BCR of 1.8

    BCR = benefits ÷ costs. X = 700/400 = 1.75, Y = 450/250 = 1.8, Z = 300/240 = 1.25. Y is highest. X has the largest net benefit (300,000), but that is not what BCR measures.

Want more Project Management PMP questions?

Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.

Practise free in the web app Practise on Telegram

More Project Management practice

About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.