Project Management PM fundamentals (CAPM) practice questions
10 free questions with answers and explanations. Try each one, then tap “Show answer”.
- Scheduling
1. Activities: A (6 days) → B (5 days) → D (8 days); A → C (8 days) → D; and E (11 days) → D. All paths end with D. What is the project duration?
- A. 22 days
- B. 38 days
- C. 19 days
- D. 14 days
Show answer
Answer: A. 22 days
Paths: A-B-D = 19, A-C-D = 22, E-D = 19. The critical path is the longest: 22 days.
- Concepts
2. What term describes the lowest level of the WBS, for which cost and duration can be estimated and managed?
- A. Work package
- B. Velocity
- C. Burndown chart
- D. Work breakdown structure (WBS)
Show answer
Answer: A. Work package
A work package: the lowest level of the WBS, for which cost and duration can be estimated and managed.
- Scheduling
3. Activities: A (3 days) → B (7 days) → D (5 days); A → C (3 days) → D; and E (8 days) → D. All paths end with D. What is the project duration?
- A. 10 days
- B. 11 days
- C. 15 days
- D. 26 days
Show answer
Answer: C. 15 days
Paths: A-B-D = 15, A-C-D = 11, E-D = 13. The critical path is the longest: 15 days.
- Earned value
4. PV = £810k, EV = £760k, AC = £470k. What is the schedule variance (SV)?
- A. −£340k
- B. £290k
- C. −£50k
- D. £50k
Show answer
Answer: C. −£50k
SV = EV − PV = 760 − 810 = -50 (behind schedule).
- Estimating
5. Using PERT (beta) estimating, an activity has optimistic 10 days, most likely 15 days and pessimistic 20 days. What is the expected duration?
- A. 16 days
- B. 15 days
- C. 17 days
- D. 13 days
Show answer
Answer: B. 15 days
E = (O + 4M + P) ÷ 6 = (10 + 60 + 20) ÷ 6 = 15 days.
- Earned value
6. EV = £100k and PV = £120k. What is the schedule performance index (SPI)?
- A. 0.83
- B. 0.93
- C. 1.83
- D. 1.2
Show answer
Answer: A. 0.83
SPI = EV ÷ PV = 100 ÷ 120 = 0.83. Below 1 = behind schedule.
- Earned value
7. EV = £100k and PV = £150k. What is the schedule performance index (SPI)?
- A. 1.67
- B. 1.5
- C. 0.77
- D. 0.67
Show answer
Answer: D. 0.67
SPI = EV ÷ PV = 100 ÷ 150 = 0.67. Below 1 = behind schedule.
- Earned value
8. EV = £90k and AC = £200k. What is the cost performance index (CPI), and what does it mean?
- A. -110 — on budget
- B. 0.45 — over budget
- C. 0.45 — under budget
- D. 2.22 — under budget
Show answer
Answer: B. 0.45 — over budget
CPI = EV ÷ AC = 90 ÷ 200 = 0.45. Below 1 means over budget; above 1 means under budget.
- Scheduling
9. Activities: A (5 days) → B (4 days) → D (7 days); A → C (5 days) → D; and E (9 days) → D. All paths end with D. What is the project duration?
- A. 30 days
- B. 10 days
- C. 16 days
- D. 17 days
Show answer
Answer: D. 17 days
Paths: A-B-D = 16, A-C-D = 17, E-D = 16. The critical path is the longest: 17 days.
- Concepts
10. MoSCoW is best described as
- A. uncontrolled expansion of scope without adjustments to time, cost and resources
- B. a chart showing the work remaining over time
- C. a prioritization technique: must have, should have, could have, won't have this time
- D. the amount of time an activity can be delayed without delaying the project end date
Show answer
Answer: C. a prioritization technique: must have, should have, could have, won't have this time
MoSCoW: a prioritization technique: must have, should have, could have, won't have this time.
Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.
Practise free in the web app Practise on TelegramMore Project Management practice
About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.