Project Management APM PFQ practice questions
10 free questions with answers and explanations. Try each one, then tap “Show answer”.
- Earned value
1. EV = £52,000, PV = £50,000. What is the schedule performance index (SPI)?
- A. 1.04
- B. 0.88
- C. 1.18
- D. 0.96
Show answer
Answer: A. 1.04
SPI = EV ÷ PV = 1.04. On or ahead of schedule.
- Responsibility
2. In a RACI chart, the 'A' stands for
- A. Accountable
- B. Assigned
- C. Available
- D. Approved
Show answer
Answer: A. Accountable
Responsible, Accountable, Consulted, Informed.
- Earned value
3. EV = £45,000, PV = £50,000. What is the schedule performance index (SPI)?
- A. 0.9
- B. 1.11
- C. 0.82
- D. 1.1
Show answer
Answer: A. 0.9
SPI = EV ÷ PV = 0.9. Behind schedule.
- Exam
4. The APM PFQ exam consists of
- A. 60 multiple-choice questions in 1 hour
- B. 30 essay questions in 3 hours
- C. 100 questions in 2 hours
- D. a practical project
Show answer
Answer: A. 60 multiple-choice questions in 1 hour
The pass mark is 60%.
- Change
5. Uncontrolled growth in project scope is called
- A. crashing
- B. gold plating only
- C. float
- D. scope creep
Show answer
Answer: D. scope creep
Change control helps prevent it.
- Risk
6. Which is a response to a threat?
- A. Enhance
- B. Exploit
- C. Celebrate
- D. Avoid
Show answer
Answer: D. Avoid
Threat responses include avoid, reduce, transfer and accept.
- Earned value
7. EV = £45,000, AC = £55,000. What is the cost performance index (CPI)?
- A. 0.9
- B. 0.82
- C. 1.22
- D. 0.91
Show answer
Answer: B. 0.82
CPI = EV ÷ AC = 0.82. Over budget.
- Risk
8. The difference between a risk and an issue is that
- A. a risk may happen; an issue has already happened
- B. risks only affect cost
- C. an issue may happen; a risk has happened
- D. they are the same
Show answer
Answer: A. a risk may happen; an issue has already happened
Issues need resolving now.
- Earned value
9. EV = £60,000, AC = £40,000. What is the cost performance index (CPI)?
- A. 0.67
- B. 2.5
- C. 1
- D. 1.5
Show answer
Answer: D. 1.5
CPI = EV ÷ AC = 1.5. Under or on budget.
- Stakeholders
10. Stakeholders with high power and high interest should usually be
- A. ignored
- B. monitored only
- C. kept informed only
- D. managed closely
Show answer
Answer: D. managed closely
From the power/interest grid.
Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.
Practise free in the web app Practise on TelegramMore Project Management practice
About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.