12,900+ practice questions · 144 exams · new questions added every week

Project Management APM PFQ practice questions

10 free questions with answers and explanations. Try each one, then tap “Show answer”.

  1. Earned value

    1. EV = £52,000, PV = £50,000. What is the schedule performance index (SPI)?

    • A. 1.04
    • B. 0.88
    • C. 1.18
    • D. 0.96
    Show answer

    Answer: A. 1.04

    SPI = EV ÷ PV = 1.04. On or ahead of schedule.

  2. Responsibility

    2. In a RACI chart, the 'A' stands for

    • A. Accountable
    • B. Assigned
    • C. Available
    • D. Approved
    Show answer

    Answer: A. Accountable

    Responsible, Accountable, Consulted, Informed.

  3. Earned value

    3. EV = £45,000, PV = £50,000. What is the schedule performance index (SPI)?

    • A. 0.9
    • B. 1.11
    • C. 0.82
    • D. 1.1
    Show answer

    Answer: A. 0.9

    SPI = EV ÷ PV = 0.9. Behind schedule.

  4. Exam

    4. The APM PFQ exam consists of

    • A. 60 multiple-choice questions in 1 hour
    • B. 30 essay questions in 3 hours
    • C. 100 questions in 2 hours
    • D. a practical project
    Show answer

    Answer: A. 60 multiple-choice questions in 1 hour

    The pass mark is 60%.

  5. Change

    5. Uncontrolled growth in project scope is called

    • A. crashing
    • B. gold plating only
    • C. float
    • D. scope creep
    Show answer

    Answer: D. scope creep

    Change control helps prevent it.

  6. Risk

    6. Which is a response to a threat?

    • A. Enhance
    • B. Exploit
    • C. Celebrate
    • D. Avoid
    Show answer

    Answer: D. Avoid

    Threat responses include avoid, reduce, transfer and accept.

  7. Earned value

    7. EV = £45,000, AC = £55,000. What is the cost performance index (CPI)?

    • A. 0.9
    • B. 0.82
    • C. 1.22
    • D. 0.91
    Show answer

    Answer: B. 0.82

    CPI = EV ÷ AC = 0.82. Over budget.

  8. Risk

    8. The difference between a risk and an issue is that

    • A. a risk may happen; an issue has already happened
    • B. risks only affect cost
    • C. an issue may happen; a risk has happened
    • D. they are the same
    Show answer

    Answer: A. a risk may happen; an issue has already happened

    Issues need resolving now.

  9. Earned value

    9. EV = £60,000, AC = £40,000. What is the cost performance index (CPI)?

    • A. 0.67
    • B. 2.5
    • C. 1
    • D. 1.5
    Show answer

    Answer: D. 1.5

    CPI = EV ÷ AC = 1.5. Under or on budget.

  10. Stakeholders

    10. Stakeholders with high power and high interest should usually be

    • A. ignored
    • B. monitored only
    • C. kept informed only
    • D. managed closely
    Show answer

    Answer: D. managed closely

    From the power/interest grid.

Want more Project Management APM PFQ questions?

Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.

Practise free in the web app Practise on Telegram

More Project Management practice

About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.