Project Management PRINCE2 7 Foundation practice questions

10 free questions with answers and explanations. Try each one, then tap “Show answer”.

  1. Processes

    1. What is the purpose of 'controlling a stage'?

    • A. Assigning work, monitoring it, dealing with issues and reporting during a stage
    • B. Reviewing the current stage, planning the next and updating the business case
    • C. Confirming acceptance of the project product and providing a fixed point for project closure
    • D. Controlling the link between the project manager and the team manager(s)
    Show answer

    Answer: A. Assigning work, monitoring it, dealing with issues and reporting during a stage

    Controlling a stage: assigning work, monitoring it, dealing with issues and reporting during a stage.

  2. General

    2. What are the three tests of business justification in PRINCE2?

    • A. Desirable, viable and achievable
    • B. Planned, monitored and closed
    • C. Fast, cheap and good
    • D. Specific, measurable and achievable
    Show answer

    Answer: A. Desirable, viable and achievable

    The project must remain desirable, viable and achievable.

  3. People & organizing

    3. The senior user

    • A. is ultimately accountable for the project and owns the business case
    • B. represents those designing, developing and delivering the products and provides resources
    • C. specifies user needs and is accountable for the benefits being realized
    • D. manages the project day to day within the constraints set by the project board
    Show answer

    Answer: C. specifies user needs and is accountable for the benefits being realized

    The senior user specifies user needs and is accountable for the benefits being realized.

  4. Management products

    4. Which report is sent by the project manager to the project board at regular intervals on stage progress?

    • A. End stage report
    • B. Highlight report
    • C. Exception report
    • D. End project report
    Show answer

    Answer: B. Highlight report

    Highlight report: from the project manager to the project board at regular intervals on stage progress.

  5. Management products

    5. A end stage report is sent from

    • A. the project manager to the project board at the end of each management stage
    • B. the project manager to the project board when stage tolerances are forecast to be exceeded
    • C. the project manager to the project board when closing the project
    • D. the project manager to the project board at regular intervals on stage progress
    Show answer

    Answer: A. the project manager to the project board at the end of each management stage

    End stage report: from the project manager to the project board at the end of each management stage.

  6. General

    6. Who sets stage tolerances?

    • A. The project board
    • B. The team manager
    • C. Project support
    • D. The business layer
    Show answer

    Answer: A. The project board

    The project board delegates authority to the project manager within stage tolerances.

  7. Practices

    7. Which PRINCE2 7 practice addresses handling unplanned events such as requests for change, off-specifications and problems?

    • A. Issues
    • B. Risk
    • C. Progress
    • D. Business case
    Show answer

    Answer: A. Issues

    The issues practice: handling unplanned events such as requests for change, off-specifications and problems.

  8. Principles

    8. The principle 'manage by stages' means

    • A. tolerances are set so each level of management only escalates when they are forecast to be exceeded
    • B. the project concentrates on the definition and delivery of products and their quality requirements
    • C. the project is planned, monitored and controlled one management stage at a time
    • D. lessons are sought, recorded and acted on throughout the project
    Show answer

    Answer: C. the project is planned, monitored and controlled one management stage at a time

    Manage by stages: the project is planned, monitored and controlled one management stage at a time.

  9. Practices

    9. The purpose of the business case practice is to address

    • A. whether the project is (and remains) desirable, viable and achievable
    • B. the project's roles, responsibilities and relationships between people
    • C. handling unplanned events such as requests for change, off-specifications and problems
    • D. defining and implementing the means to create and verify fit-for-purpose products
    Show answer

    Answer: A. whether the project is (and remains) desirable, viable and achievable

    The business case practice: whether the project is (and remains) desirable, viable and achievable.

  10. General

    10. Which risk response is appropriate only for threats?

    • A. Enhance
    • B. Avoid
    • C. Exploit
    • D. Share
    Show answer

    Answer: B. Avoid

    Exploit and enhance are opportunity responses; share applies to both.

Want more Project Management PRINCE2 7 Foundation questions?

Get fresh questions every day, focused on your weak topics, plus timed mock tests. Free to start.

Practise free in the web app Practise on Telegram

More Project Management practice

About the Project Management on Mock Night · Original practice questions; not affiliated with the exam board.